Lean value stream analysis

Potential savings of over CHF 20 million in fiber optic expansion

Project context: Telecommunications – Network infrastructure – Fiber optic expansion

Investment in test application: approx. CHF 200,000

Internal effort: approx. 15–20 person-days

Result: > CHF 20 million identified savings potential over approximately 5 years

Our role: Lean management expertise, conducting value stream analysis, and providing technical guidance and coordination of the implementation team (drum beat).

The expansion of fiber optic connections resulted in high follow-up costs due to incorrectly connected lines to end customers. These errors were often only discovered after construction was completed: the manhole was already closed, the mCAN sealed, and the construction site dismantled. Following customer complaints, construction sites had to be reopened, connections checked, and errors corrected.

Lean value stream mapping visualized the end-to-end process and revealed a crucial lever: an additional inspection step immediately before construction was completed could identify errors while they were still easily correctable. Subsequently, a test application was developed that checked before and after the connection whether the same end devices or routers were detectable in the homes. Over the approximately five-year expansion phase, this identified potential savings of over CHF 20 million. 

challenges

Agenda

Results

  • Swapped connection cables
  • Late fault detection
  • High rework costs
  • Customer complaints
  • End-to-end value stream analysis
  • Causes and error origins analyzed
  • Test step and test logic derived
  • Implementation coordinated in the drum beat
  • > CHF 20 million identified savings potential
  • Fewer complaints
  • Higher customer satisfaction
  • Higher employee satisfaction

Optimization and standardization of a logistics process

Project context: Network infrastructure company

Investment: CHF 133,900

Lean Master effort: approx. 120 hours

Result: CHF 1 million target benefit over 5 years – Controlling-validated

Our role: Coaching and professional support of a Lean Master trained by us during her thesis.

In a rapidly growing company, the logistics process was organized differently across several regions. Procedures, responsibilities, and ordering processes were not standardized. This resulted in unnecessary handovers, waiting times, unclear responsibilities, and additional administrative work.

Lean value stream mapping made the end-to-end process visible. In workshops with relevant stakeholders, 39 pain points were systematically identified. The analysis showed that the root causes did not lie with individual employees, but rather in a fragmented process lacking clear end-to-end responsibility, with inconsistent roles and regionally varying procedures.

Based on this, a nationally standardized target process, clear responsibilities, earlier integration of material planning, digitalization of logistics control, and a concrete implementation roadmap were developed. The target benefit, validated by controlling, amounted to CHF 1 million over five years with a calculated investment of CHF 133,900.

challenges

Agenda

Results

  • Regional process variants
  • Unclear end-to-end responsibility
  • Unnecessary handovers and waiting times
  • High administrative and logistical effort
  • End-to-end value stream analysis
  • 39 pain points systematically recorded
  • Causes and responsibilities clarified
  • Target process and implementation roadmap developed
  • CHF 1 million target benefit over 5 years
  • Clearer responsibilities
  • Less waiting times
  • Higher customer and employee satisfaction